We don't implement the full scrum cycle, but use following elements:

  • New requirements are written down as User Stories.
  • Each feature of the User Story is a subtask.
  • If possible, a subtask holds a list of acceptance criteria.
  • User Stories are prioritized by Kurt Gerber (this should be done by the project management).
  • A sprint cycle lasts two weeks (11 days), from Monday to Thursday.
  • The standup (ca. 15 minutes) takes place on Tuesday and Thursday, 9.15.
  • A sprint starts with the sprint planning, where the developers assign themselves user stories.
  • Todo: Set date!
  • The sprint ends with a sprint review meeting where the implemented user stories are presented by the developers.
  • Date: Thursday, after lunch.
  • After the sprint review a short retro is held, where the process is discussed.
  • Developers update the status of their tickets on the agile board; the latest state is always deployed to qcat-dev.
  • To be defined:
  • Who creates new user stories / subtasks?
  • When are they created? Who is responsible for the estimates.

Updated by Sebastian Manger almost 9 years ago · 3 revisions