Agile elements¶
We don't implement the full scrum cycle, but use following elements:
- New requirements are written down as User Stories. * Each feature of the User Story is a subtask. * If possible, a subtask holds a list of acceptance criteria.
- User Stories are prioritized by Kurt Gerber (this should be done by the project management).
- A sprint cycle lasts two weeks (11 days), from Monday to Thursday.
- The standup (ca. 15 minutes) takes place on Tuesday and Thursday, 9.15.
- A sprint starts with the sprint planning, where the developers assign themselves user stories.
- Todo: Set date!
- The sprint ends with a sprint review meeting where the implemented user stories are presented by the developers.
- Date: Thursday, after lunch.
- After the sprint review a short retro is held, where the process is discussed.
- Developers update the status of their tickets on the agile board; the latest state is always deployed to qcat-dev.
- Also see: Responsibilities
- To be defined:
- Who creates new user stories / subtasks?
- When are they created? Who is responsible for the estimates.